Submitting and Accepting Offers
 |
 |
Suppliers submit their bids directly on the platform. The purchaser is not obliged to accept any of the offers.
RFI (Request for Information)
The bids submitted are not binding.
RFP (Request for Proposal)
The bids submitted are binding.
|
 |
 |
 |
Suppliers submit their bids directly on the platform. Suppliers underbid each other in the minimum bid-range laid down by the buyer. The offers submitted are binding.
Depending on what the purchaser has stipulated at the beginning of the auction, he is obliged to accept the best or one of the best offers if it is lower than the binding limit price he has set.
|
 |
 |
 |
Beginning with a low starting price defined by the purchaser, the item price is raised
round by round until either the maximum price is exceeded or a supplier submits a bid at
the current price. In this case the purchaser is obliged to accept the bid. If several bids
are submitted in the same round, the purchaser decides which of these bids he accepts.
As purchasers are obliged to accept bids submitted in a Reverse Dutch Auction they have to clarify
the conditions and all the quality requirements with the suppliers in the run-up to the auction.
During the Reverse Dutch Auction it is then determined through the offer price, which supplier is awarded
the item.
|
 |
 |
 |
In a Multi-Round Auction the price decreases round-by-round beginning with the starting price
set by the purchaser. Every supplier in the Multi-Round Auction must confirm in each round that
he is still offering at the current price by submitting a bid. In a multi-item auction the supplier must
confirm the price for each item separately. If the supplier does not confirm the price for an item
in a round, he drops out of the Multi-Round Auction for this item and the price from the preceding
round is his last valid bid for the item. In this case the supplier cannot
submit a bid for the item concerned in a later round.
The purchaser defines the acceptance of bid rule (award to one of x best bidders) and the VBO option in the master data of the
Multi-Round Auction. The acceptance of bid rule is in effect for an item, if the binding limit price for the
item has been reached or underbid by a submitted bid.
|
 |
 |
 |
Suppliers may view all Requests for Quotations, whose circles of suppliers are not restricted.
Requests for quotations with a limited circle of suppliers can be seen only by the suppliers in the respective group.
Purchasers may additionally publish a "Request for Quotation with Reply" or
a "Request for Quotation with Bid". This applies to all types of Requests for
Quotations in which the bids are submitted on fairpartners.
|
 |
Correct as at: November 2009
|